Required Operating Reserve

Scroll Prev Top Next More

HOMER Logo


The required operating reserve is the minimum amount of operating reserve that the system must be capable of providing. HOMER calculates the required operating reserve for each time step based on the values that you enter on the Constraints page. Whenever possible, HOMER ensures that enough dispatchable capacity is available to keep the operating reserve equal to or greater than the required operating reserve. HOMER records any shortfall as a capacity shortage.

Because operating reserve guards against increases in the load or decreases in the renewable power output, the required operating reserve is a function of both the load and the renewable power output (specifically, the solar and wind power output, because the hydro power output typically experiences little short-term variability). The amount of required operating reserve, therefore, typically changes from one time step to the next. In each time step, HOMER calculates the required operating reserve on the AC and DC buses using the following equations:

equations_L_res,AC

equations_L_res,DC

where:


 

 

Lres,AC

= the required operating reserve on the AC bus

 

Lres,DC

= the required operating reserve on the DC bus

 

rload

= the Operating reserve as a percent of load in the current time step variable

 

Lprim,AC

= the average AC primary load in the current time step

 

Lprim,DC

= the average DC primary load in the current time step

 

rpeakload

= the Operating reserve as a percent of annual peak load variable

 

symbols_Lhat_prim,AC

= the highest AC primary load experienced by the system during the year

 

symbols_Lhat_prim,DC

= the highest DC primary load experienced by the system during the year

 

rwind

= the Operating reserve as a percent of wind power output variable

 

Pwind,AC

= the average AC wind power output in the current time step

 

Pwind,DC

= the average DC wind power output in the current time step

 

rsolar

= the Operating reserve as a percent of solar power output variable

 

PPV

= the average PV array output in the current time step

See also

Maximum Annual Capacity Shortage

Total Capacity Shortage

Capacity Shortage Fraction