Show/Hide Toolbars

HOMER Pro 3.16

Navigation: Glossary

Other Operation and Maintenance Cost

Scroll Prev Top Next More

HOMER Logo


 

Type:

Output Variable

Units:

$/yr

Symbol:

Com,other

The other O&M cost is the sum of the system fixed O&M cost, the penalty for capacity shortage, and the penalties for emissions of pollutants.

HOMER uses the following equation to calculate the other O&M cost:

equations_C_om,other

where:


 

 

Com,fixed

= system fixed O&M cost [$/yr]

 

Ccs

= the penalty for capacity shortage [$/yr]

 

Cemissions

= the penalty for emissions [$/yr]

HOMER uses the following equation to calculate the penalty for capacity shortage:

equations_C_cs

where:


 

 

ccs

= capacity shortage penalty [$/kWh]

 

Ecs

= total capacity shortage [kWh/yr]

HOMER uses the following equation to calculate the penalty for emissions:

equations_C_emissions

where:



 

cCO2

= penalty for emissions of CO2 [$/t]

 

cCO

= penalty for emissions of CO [$/t]

 

cUHC

= penalty for emissions of unburned hydrocarbons (UHC) [$/t]

 

cPM

= penalty for emissions of particulate matter (PM) [$/t]

 

cSO2

= penalty for emissions of SO2 [$/t]

 

cNOx

= penalty for emissions of NOx [$/t]

 

MCO2

= annual emissions of CO2 [kg/yr]

 

MCO

= annual emissions of CO [kg/yr]

 

MUHC

= annual emissions of unburned hydrocarbons (UHC) [kg/yr]

 

MPM

= annual emissions of particulate matter (PM) [kg/yr]

 

MSO2

= annual emissions of SO2 [kg/yr]

 

MNOx

= annual emissions of NOx [kg/yr]

You can specify the penalties for each pollutant on the Emissions page. For information on how HOMER calculates the emissions of each pollutant, see the How HOMER calculates emissions section of the help.